Bago Quarry Planning Agreement

Consultation has concluded

Council has received an offer to enter into a voluntary planning agreement in connection with Development Application 2014-0960 for increased extraction at Bago Quarry, located at Lot 129 DP 754445, 129 Milligans Road, Herons Creek.

The planning agreement provides for:

  • The Developer to pay monetary Development Contributions to Council of $0.18 per tonne, above the first 30,000 tonnes, towards the maintenance and upgrade of Bago Road;
  • Maintenance works to be undertaken by the Developer on approximately 2.1 kilometres of Milligan’s Road, Herons Creek.

The draft planning agreement can be viewed at Council’s Customer Service offices in

  • Burrawan Street, Port Macquarie;
  • High Street Wauchope; and
  • Bold Street, Laurieton

between 8.30am and 4.30pm on normal business weekdays until the end of the notification period on Friday 24 July 2015.

Submissions close Friday 24 July 2015.

Submissions will be accepted via post, email or online using the form below.

The General Manager
Port Macquarie-Hastings Council
PO Box 84
Port Macquarie NSW 2444
Email council@pmhc.nsw.gov.au

For any enquiries relating to the planning agreement, please contact Vanessa Penfold on 6581 8111 or e-mail council@pmhc.nsw.gov.au


Council has received an offer to enter into a voluntary planning agreement in connection with Development Application 2014-0960 for increased extraction at Bago Quarry, located at Lot 129 DP 754445, 129 Milligans Road, Herons Creek.

The planning agreement provides for:

  • The Developer to pay monetary Development Contributions to Council of $0.18 per tonne, above the first 30,000 tonnes, towards the maintenance and upgrade of Bago Road;
  • Maintenance works to be undertaken by the Developer on approximately 2.1 kilometres of Milligan’s Road, Herons Creek.

The draft planning agreement can be viewed at Council’s Customer Service offices in

  • Burrawan Street, Port Macquarie;
  • High Street Wauchope; and
  • Bold Street, Laurieton

between 8.30am and 4.30pm on normal business weekdays until the end of the notification period on Friday 24 July 2015.

Submissions close Friday 24 July 2015.

Submissions will be accepted via post, email or online using the form below.

The General Manager
Port Macquarie-Hastings Council
PO Box 84
Port Macquarie NSW 2444
Email council@pmhc.nsw.gov.au

For any enquiries relating to the planning agreement, please contact Vanessa Penfold on 6581 8111 or e-mail council@pmhc.nsw.gov.au