Update September 2016

over 3 years ago

Clearing works are complete on both Stages 2 and 3.

Bulk earthworks are well progressed on Stage 2 at 75% complete with permanent pavement works in progress at the eastern and western end of this stage. Commuters will experience the first section of permanent works, a 600m length at the eastern end of Stage 2 approaching Forest Parkway with the traffic switch undertaken on Wednesday 05 October 2016.

Stage 3 works are progressing well with temporary works completed adjacent Long Point Drive allowing the Contract works to progress on the southern side of Houston Mitchell Drive. Current works underway include stormwater drainage works, bulk earthworks and foundation treatments