Works near completion

almost 3 years ago

Works are nearing completion on Houston Mitchell Drive with the final sections of works sealed and opened to traffic. Portable signals were removed on Thursday 27 July 2017. Wet weather and challenging subgrade conditions have impeded completion of the Works with over 4 months impact to the Project.

In the coming weeks, finalisation works will be undertaken from the road shoulder to complete surface water drainage, landscaping, signage and delineation. Line marking is currently scheduled for the end of August.

This important infrastructure Project has involved the realignment and reconstruction of over 4km of Houston Mitchell Drive. These works improve the safety standards of the major road for the benefit of all road users, including pedestrian and cyclists and provide a 3.25m travel lane with a 2m sealed shoulder and 1m verge in each direction.