North Shore Sewerage

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

Update:

Piping work under the river is now complete almost 2 months ahead of schedule. The focus now is on completing the street mains so that more than 280 properties can be connected to the new network.

To read the full media release issued 12 November 2015 - North Shore sewer goes underground

Update:

Piping work under the river is now complete almost 2 months ahead of schedule. The focus now is on completing the street mains so that more than 280 properties can be connected to the new network.

To read the full media release issued 12 November 2015 - North Shore sewer goes underground

Consultation has concluded
  • What has happened so far

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    In December 2012 Council made a committment to deliver reticulated sewer services to the villages of North Shore, Comboyne, Long Flat and Telegraph Point by August 2016.

    Areas of the North Shore to be served includes Riverside Drive, Shoreline Drive, Corilla Estate and Sandfly Alley.

    Council has contracted Ledonne Constructions and Pressure System Solutions P/L to facilitate the planning of the installation of the pressure sewer pump units and associated equipment within each property.

    Ledonne Constructions have now visited properties in the North Shore Sewerage Scheme to discuss the system, assess installation parameters and to review external plumbing.

  • North Shore Sewerage Scheme 'drop-in' Information Session

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Council held a ‘drop-in’ session on Monday 22 June 2015 at North Shore Rural Fire Shed, Shoreline Dr, North Shore, from 3.00pm to 7.00pm.

    Council and Ledonne Constructions representatives were in attendance to discuss any matters concerning the proposed scheme. Examples of the pressure sewer units and draft designs were available for discussion.





  • North Shore Sewerage Scheme Community Information Session

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CLOSED: This map consultation has concluded
    supporting image

    This meeting has occurred. You can still download the fact sheet for more information.

    Map of workA community information session will be held to correspond with the North Shore Progress Association Annual General Meeting.

    This meeting will be held 7.00pm Wednesday 20 November at the Fire Station in Shoreline Drive.

    Come along, find out more and have your say.