Town Square progress report

Developments at Town Square have been progressing well with the following works:

  • Service relocations complete
  • In situ concrete works are now more than 50% complete
  • Concrete and bluestone paving works commencing this week.
  • The majority of tree planter beds and light post footings have been installed
  • Underground electrical reticulation mostly complete
  • Footpaths progressively being reconstructed.
  • Works are generally on program.