Town Square progress report
Developments at Town Square have been progressing well with the following works:
- Service relocations complete
- In situ concrete works are now more than 50% complete
- Concrete and bluestone paving works commencing this week.
- The majority of tree planter beds and light post footings have been installed
- Underground electrical reticulation mostly complete
- Footpaths progressively being reconstructed.
- Works are generally on program.