Dual lanes on Ocean Drive between Matthew Flinders Drive to Greenmeadows Drive, Port Macquarie are being planned.
Council is planning to upgrade around 3.4 kilometres of Ocean Drive from two lanes to four lanes between Matthew Flinders Drive to Greenmeadows Drive (South), Port Macquarie.
Council has received funds of $10 million from the NSW State Government, which will complete the design, environmental assessment and planning approval for this project and contribute to construction.
Click image to expand
The construction program is yet to be determined and is subject to further funding.
Further information is available below in the updates tab or on our Council website.
For ongoing information about this project please see the project webpage.
Dual lanes on Ocean Drive between Matthew Flinders Drive to Greenmeadows Drive, Port Macquarie are being planned.
Council is planning to upgrade around 3.4 kilometres of Ocean Drive from two lanes to four lanes between Matthew Flinders Drive to Greenmeadows Drive (South), Port Macquarie.
Council has received funds of $10 million from the NSW State Government, which will complete the design, environmental assessment and planning approval for this project and contribute to construction.
Click image to expand
The construction program is yet to be determined and is subject to further funding.
Further information is available below in the updates tab or on our Council website.
Share Registering for Ocean Drive Duplication updates. on FacebookShare Registering for Ocean Drive Duplication updates. on TwitterShare Registering for Ocean Drive Duplication updates. on LinkedinEmail Registering for Ocean Drive Duplication updates. link
Click here to play video
Concept design only - Ocean Drive fly through video
The final visualisation for consultation - SMEC Ocean Drive Duplication Project. This is a concept only.
Life Cycle
Preliminary scoping of project
Ocean Drive Duplication has finished this stage
November and December 2013, first round community consultation.
Consultation and Design
Ocean Drive Duplication has finished this stage
Consultation with the local community and detailed design and preconstruction approval for duplication work.
Community information sessions
Ocean Drive Duplication has finished this stage
25 & 27 February 2016 - Community information sessions will be conducted by the project team, including staff from Council and SMEC. This is the first in a series of community information sessions that will be held this year.
Second round community information
Ocean Drive Duplication has finished this stage
Come along and talk with representatives from Council and project contractors SMEC at one of two drop in sessions being held:
Where:
Emerald Downs Community Centre. Corner of Ocean and Emerald Drives Lower Level, Lighthouse Plaza Shopping Centre
When:
Thursday 2 June, drop in between 4pm-7pm Saturday 4 June, drop in between 10am - 1pm
Final design is being developed
Ocean Drive Duplication has finished this stage
Final Design - Third round community information pop in sessions
Ocean Drive Duplication has finished this stage
The community is invited to view the final design for the Ocean Drive Duplication and find out more about the project at one of two drop‑in sessions.
Where:
Emerald Downs Community Centre
Corner of Ocean Drive and Emerald Drive Lower Level Lighthouse Plaza Shopping Centre Port Macquarie
When:
Thursday 25 May 2017
Drop in between 4pm and 7pm
Saturday 27 May 2017
Drop in between 1pm and 4pm
Community engagement concludes