Town Green:
- Existing pathways have been removed.
- Existing power and lighting facilities have been
removed
- 2500t of large rock has been added to the existing
seawall and is complete
- Storm water upgrades and water main relocation is
complete
- 5m wide restaurant promenade is complete
- 5m wide coloured concrete foreshore path is nearing
completion
- Provision of irrigation systems throughout the site
have commenced
- Linking pathways between foreshore path and restaurant
promenade will commence in the coming weeks
- New restaurant promenade lighting, seating and
established plants to be installed in the coming weeks
- New turf and garden landscaping to commence in the coming
weeks
- Works are due for completion November 2017 (weather
permitting)
- Works are progressing ahead of schedule
Town Square:
- New concrete surfaces are approximately 70%
complete
- Concrete and stone paving works have commenced
to the northern end of the site and are moving south progressively
- The majority of light pole footings and planter
boxes have been installed
- All underground electrical and water services
have been installed
- Light poles are due to be delivered in coming
weeks
- Mature trees and plants are due to be installed
from next week
- Cenotaph embellishment works are currently being
undertaken with memorial plinths already having been relocated and stone
cladding works due to commence this week
- The cenotaph will be available for remembrance
day as previously reported
- Works are progressing as per schedule and are due for
completion prior to the busy Christmas holiday period in mid-December this
year (weather permitting)