Town Green and Town square works marching along
Town Green:
- Existing pathways have been removed.
- Existing power and lighting facilities have been removed
- 2500t of large rock has been added to the existing seawall and is complete
- Storm water upgrades and water main relocation is complete
- 5m wide restaurant promenade is complete
- 5m wide coloured concrete foreshore path is nearing completion
- Provision of irrigation systems throughout the site have commenced
- Linking pathways between foreshore path and restaurant promenade will commence in the coming weeks
- New restaurant promenade lighting, seating and established plants to be installed in the coming weeks
- New turf and garden landscaping to commence in the coming weeks
- Works are due for completion November 2017 (weather permitting)
- Works are progressing ahead of schedule
Town Square:
- New concrete surfaces are approximately 70% complete
- Concrete and stone paving works have commenced to the northern end of the site and are moving south progressively
- The majority of light pole footings and planter boxes have been installed
- All underground electrical and water services have been installed
- Light poles are due to be delivered in coming weeks
- Mature trees and plants are due to be installed from next week
- Cenotaph embellishment works are currently being undertaken with memorial plinths already having been relocated and stone cladding works due to commence this week
- The cenotaph will be available for remembrance day as previously reported
- Works are progressing as per schedule and are due for completion prior to the busy Christmas holiday period in mid-December this year (weather permitting)
Share Town Green and Town square works marching along on Facebook
Share Town Green and Town square works marching along on Twitter
Share Town Green and Town square works marching along on Linkedin
Email Town Green and Town square works marching along link
Thank you for your interest in this project. Consultation has now concluded.